The order of work should reflect what happens beneath each part of the roof. A useful tender tells contractors which areas the occupier can release and when.
Start with a plan of the operation
Mark dispatch bays, production areas, offices, stock and shared access routes on a single drawing. Record which activities can move, which must continue and who can agree a change. A loading bay used for one early delivery may need a different arrangement from a dispatch area in continuous use.
Ask each tenderer to price the same constraints
Give bidders the permitted working hours, delivery windows and storage areas. Ask them to mark their proposed work zones, sequence and temporary protection. If one price assumes an empty warehouse and another allows for live operations, resolve the difference before appointing a contractor.
Agree how each area returns to use
Identify who confirms a zone can reopen, what notice tenants need and who receives the next programme update. At The Podium in Bath, Premierseal replaced flat roofs above an occupied retail facility. Limited space for hoisting and storage made logistics part of the programme from the outset.
A phase sheet for the tender
Prepare one sheet per work zone. For a dispatch bay, show the boundary on a plan, the times lorries use it, where materials could be landed and who can release the area. Ask each tenderer to mark where these requirements change the sequence or the price.
- Which activities must continue below this zone?
- What access, storage or delivery restriction affects this phase?
- What must be handed back before the next zone is released?