A replacement roof tender needs a clear boundary at the drainage system. An assumption about where one contractor stops can leave an important detail unpriced.
Trace the scope to an agreed point
Identify gutters, outlets, overflows and connections serving the work area. Mark where the roofing package finishes and who deals with each connection. Distinguish the known condition from areas still to be inspected.
Separate cleaning from refurbishment
A photograph of debris can justify inspection. Deciding whether the gutter needs replacement or whether its capacity suits a revised scheme requires further evidence. Identify who will assess any drainage question and what bidders should allow for.
Set out the temporary arrangements
Ask how the bidder proposes to manage water while an area is open and how occupation affects access. Request itemised prices for agreed gutter and outlet works, with exclusions shown.
Draw the boundary on the tender plan
For an internal gutter serving two units, mark the first connection outside the work zone. Identify who investigates the shared section. If one occupier has reported water entry, record that observation separately from the extent the client has authorised.
- Which outlets and connections form part of the package?
- Who assesses outstanding condition or capacity questions?
- Which adjoining unit needs access or temporary arrangements?