Two prices for the same roof can cover different work. Before advising a client, make each tenderer’s allowances and exclusions visible against the same schedule.
Compare the interfaces first
Set out separate lines for the roof covering, insulation, rooflights, outlets, perimeter details, access and temporary protection. Record whether each item is included, excluded or provisional. A price for a new covering tells the client little about responsibility for the junction with the existing building.
Test the programme assumptions
Ask all bidders to state the work zones, proposed access, working hours and any period when the occupier must release space. Check that each return uses the same information. A shorter programme is hard to compare if it relies on unrestricted deliveries or a closed loading bay.
Issue one clarification schedule
For each material difference, ask a specific question and record the answer beside the original price. Ask for a revised amount where it changes the scope. Keep the agreed clarifications with the recommendation so the client can see what the chosen tender buys.
A clarification you can send to tenderers
Suppose one return allows for replacing the outlets and another simply says “outlets included”. Ask each bidder to identify the number, the connection point and any work to the downpipe. Record the answer beside the price before taking a headline saving to the client.
- Is each disputed item included, excluded or provisional?
- What quantity and access arrangement underlie the price?
- Has the tenderer confirmed the effect of the clarification on price and programme?