Planning a commercial roof replacement beneath an existing solar PV array

    An existing solar array changes the scope of a re-roof. Before issuing a tender, establish who controls the installation and who can authorise work affecting it.

    Establish who does what

    Collect the layout, asset information and contact route for the operator. Identify who coordinates specialist electrical work and any removal, storage and reinstatement. Put each responsibility on the tender schedule for the appropriate party to price.

    Ask for a roof plan and a sequence

    Show the array, proposed roof zones, access routes and storage space. Give bidders the operational constraints and ask which activities depend on another contractor. Resolve any conflict with space the occupier uses daily.

    Define the handback

    Agree which parties supply records for the roof and reinstated PV installation. Ask for exclusions and outstanding decisions. The owner can then see which further appointments the project requires.

    Resolve the release date

    If the tender assumes the array has been removed, establish who makes that appointment, when the area becomes available and what happens if only part can be released. This puts roofing prices on a common basis.

    • Who controls the array and authorises specialist work?
    • Which party allows for each movement and storage requirement?
    • What must happen before the next zone is released?

    Related service: commercial roof replacement.